To campaign for excellent customer service from our developer, Al Hamra Estates, and to work with Al Hamra Estates to achieve the dream that is Al Hamra Village.

To promote investor interests and to act as a channel for promoting investors interests

alhamradreams@gmail.com

4 Comments

  1. Adam Huss said,

    25 January 2009 at 4:34 am

    Hi,

    Great to see this happening.

    Will someone please put me on their mailing list to receive progress reports so i can keep up to scratch with progress. Have also bought in Royal Breeze.

    Cheers

    Adam – UK

  2. 6 March 2009 at 3:47 pm

    My wife and I bought into Al Hamra at the begining.
    We have other property in Dubai under construction, well some is.
    Please may we/I be included in your mailing list.

    Regards,

    Steve.

  3. denny said,

    30 March 2009 at 12:58 pm

    An Update on Al Hamra Village (Sent on 30th March 09)

    Dear Customer,

    We take great pleasure in informing you that Marina Building E, F, G & H are nearing completion and we have appended details of the pending tasks and estimated handover dates for each of the buildings, for your perusal. We shall write to you soon again for the handover of your property. This mail is just to prepare you for the handover. We have already handed over 200 town houses and Marina, A to D apartments.

    Building Pending Tasks Estimated date for handover

    Marina E Final Testing/inspection & painting 30th of April 09

    Marina F commissioning of electricity, A/C, testing, inspection and final painting 5th of June 2009

    Marina G commissioning of electricity, A/C, testing, inspection and final painting 5th of July 2009

    Marina H Wood joinery, aluminum work, commissioning of electricity, A/C, testing, inspection and final painting. (Currently painting is being done).
    5th of September 2009
    Kindly make necessary arrangements for finances, interior designing, etc.

    We take great pride in informing you that the Al Hamra Mall is functional now and we have also attached details of the pending task of the Marina Club House and the completion schedule. We shall keep you updated about the other developments, but in the meantime should you need any more information, please do get in touch with us.

    We also take this opportunity to reiterate that we value your patronage and look forward to a long standing relationship which is mutually beneficial.

    Best Regards

  4. Christian said,

    17 April 2009 at 5:02 pm

    Does anyone have any information with regard to the later towers in the RB to be constructed, if RAK is anything like Dubai then a number of projects will be quietly cancelled. I have an apartment in RB8 and don’t know if I should make any further payments, help!


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: